Blair Avenue Project
Posted October 13, 2014 at 10:44 am by Tim Dustrude
Here’s a note about progress on the Blair Avenue project from Town Administrator Duncan Wilson…
On Friday, October 10th, project contractor Mike Carlson Enterprises finished the second and final lift of asphalt on the southern portion of Blair Avenue. The sidewalks in this area will be poured during the week of October 20th. In the interim, the sidewalk area should be open for access to all business along the south side of Blair. Work continues on other areas of the Project during the week of October 13, 2014.
Depending on cooperation from the weather, the paving in the intersection of Park and Blair should be completed by October 17th, as should the final lift of asphalt on the northern half of Blair. If the paving is completed as hoped, the south side of Blair is scheduled to be open for traffic by October 17.
The contractor and OPALCO are continuing with the installation of the street lighting this week and should begin the installation of street trees and grates. The Town of Friday Harbor will update information regarding the completion schedule on Wednesday, October 15th as more is known regarding any weather delays. The Town again thanks all businesses and citizens for their patience and cooperation as we near the end of the project.
You can support the San Juan Update by doing business with our loyal advertisers, and by making a one-time contribution or a recurring donation.
Categories: Around Here
One comment:
One comment...
Thanks to Mike Carlson and his dedicated crew who have been putting in long hours; working hard to get this much needed project completed. You guys ROCK!.
By submitting a comment you grant the San Juan Update a perpetual license to reproduce your words and name/web site in attribution. Inappropriate, irrelevant and contentious comments may not be published at an admin's discretion. Your email is used for verification purposes only, it will never be shared.