Construction Update: Week of August 29th, 2016
Posted August 28, 2016 at 5:50 am by Tim Dustrude
Town of Friday Harbor – Waterline Replacement Project
Locations of work:
- Underground construction is complete except for tie-in locations
- This week, Contractor is scheduled to tie-in the new waterline at the following locations:
- Douglas and San Juan Valley Rd.
- Spring St. at the Water Maintenance Facility
- San Juan Valley Rd. near the EMS/Hospital
Work Days/Hours
- Monday – Friday; 7AM-7PM
- Monday Night 9PM – 9AM shift to make waterline tie-ins
What to expect:
- As we get close to completing the water main installation; there will be an impact on traffic heading into Town from San Juan Valley Rd. There will be several active work areas between the EMS/Hospital to Water Storage Tank on Spring St. 20 minute delays will be likely in this area
- Please avoid if possible; however traffic control representatives will be on-site at all times to assist commuters.
Detours:
You can bypass our construction by using the following alternative routes to detour in or out of Town.
- Beaverton valley Road
- No. 2 School House Road
- Douglas Road
- Bailer Hill Road
Any questions or concerns please feel free to call (360) 378-0360
You can support the San Juan Update by doing business with our loyal advertisers, and by making a one-time contribution or a recurring donation.
Categories: Community, Transportation
One comment:
One comment...
I really appreciate the excellent job of communicating the projects status and updates. Bob
By submitting a comment you grant the San Juan Update a perpetual license to reproduce your words and name/web site in attribution. Inappropriate, irrelevant and contentious comments may not be published at an admin's discretion. Your email is used for verification purposes only, it will never be shared.