Update on Spring Street Pocket Park
Posted March 13, 2017 at 4:55 pm by Tim Dustrude
Mike Carlson shares this update on the construction progress for the new Spring Street Pocket Park…
The Pocket Park is now beginning to take shape.
Most of the underground work has been completed. This week, the bases for the paver borders, benches and sculptures will be formed and poured.
As soon as those are completed and the weather permits, the crews will close the upper curb and install the large storm water curb inlet, then commence to place the final concrete walks and paver surface.
Finally, the saw cut grid, benches, planting soils, irrigation and vegetation will be installed near the end of March and first part of April.
– Mike Carlson (President MCE)
You can support the San Juan Update by doing business with our loyal advertisers, and by making a one-time contribution or a recurring donation.
Categories: Community, Government
One comment:
One comment...
This is so great!
By submitting a comment you grant the San Juan Update a perpetual license to reproduce your words and name/web site in attribution. Inappropriate, irrelevant and contentious comments may not be published at an admin's discretion. Your email is used for verification purposes only, it will never be shared.