Spring Street Pocket Park Construction Update
Posted April 10, 2017 at 3:56 pm by Tim Dustrude
This is a construction update on what to expect today through the remainder of the week.
The pavers have been installed but the final concrete pour was cancelled last Friday due to bad weather. The Contractor is now scheduled to pour the balance of the concrete on Wednesday, April 12th. This portion of sidewalk will be closed to pedestrians during the pour and will reopen after the concrete has time to set.
After the concrete has been finished the crews will excavate the planting beds, install top soil, plants, irrigation, art elements, benches and pavement patching.
Appropriate signage will be placed during this phase of the project. Every effort will be made to limit interruption to businesses.
Questions regarding the project may be made to Town Hall at (360) 378-2810, or the on-site Project Manager. As always, the Town appreciates the continued patience of business owners, residents and visitors.
You can support the San Juan Update by doing business with our loyal advertisers, and by making a one-time contribution or a recurring donation.
Categories: Government, Transportation
One comment:
One comment...
Please allow busking.
By submitting a comment you grant the San Juan Update a perpetual license to reproduce your words and name/web site in attribution. Inappropriate, irrelevant and contentious comments may not be published at an admin's discretion. Your email is used for verification purposes only, it will never be shared.