Paving this Week
Posted May 8, 2017 at 1:41 pm by Tim Dustrude
Street resurfacing is scheduled to begin tomorrow on Spring Street, followed by Price Street.
Tuesday, May 9th through Friday, May 12th
Richard Lawson Construction (RLC) will resurface the portion of Spring Street between Peace Island Hospital (near Airport Circle) and Marguerite Place on Tuesday, May 9th and Wednesday, May 10th. This work is intended to repair the road where trenching occurred in 2016 for the Water Transmission Line Replacement Project.
RLC will then resurface the portion of Price Street from Spring Street to Holli Place on Thursday, May 11th and Friday, May 12th. This work is intended to repair potholing and smooth both lanes up to the portion between Holli Place and Park Street. The remaining portion will require more extensive repairs that will be scheduled following Park Street improvements.
Crews are authorized to work from 7AM to 7PM. RLC will use flaggers to direct traffic on both projects. During work hours, traffic will be reduced to a single lane and speeds lowered for the construction zone. The work zones will reopen in the evenings.
Drivers should expect delays and, if possible, plan alternate routes to ease congestion. Please slow down, pay attention and abide by the traffic control for your safety and the safety of others.
Questions and comments can be forwarded to Town Hall at (360) 378-2810.
You can support the San Juan Update by doing business with our loyal advertisers, and by making a one-time contribution or a recurring donation.
Categories: Transportation
No comments yet. Be the first!
By submitting a comment you grant the San Juan Update a perpetual license to reproduce your words and name/web site in attribution. Inappropriate, irrelevant and contentious comments may not be published at an admin's discretion. Your email is used for verification purposes only, it will never be shared.