Road Work Ahead on Spring Street and San Juan Valley Rd.

Posted August 2, 2016 at 5:15 am by

Traffic was a little slow this afternoon heading out of town on Spring Street. We heard from Town Clerk Amy Taylor about what we can expect this week…

Road Work Ahead - Peggy Sue McRae Photo

Road Work Ahead – Peggy Sue McRae Photo

Town of Friday Harbor Waterline Replacement Project Construction Update. What to expect week of August 1st.

Location(s) of work:

  • The new waterline has been installed from the WTP on Wold Rd. to intersection of San Juan Valley Rd. and Douglas Rd. This week ICI will be installing services and lateral piping at various locations along the completed section of waterline.
  • Work will be concentrated on San Juan Valley Rd between the EMS/Hospital facility and the Water Maintenance Facility on Spring St.
  • Work is also ongoing along San Juan Valley Rd. to grade and prepare the roadway for final restoration.

Work Days/Hours

  • Monday – Friday
  • Normal hours: 7AM to 7PM

What to expect: During the installation of the new water main and services there will be some impact to local private properties as crews will be installing new water meter boxes and services to some homes, there will be a time when driveway entrances and side roads will be affected for short durations during the installation. These specific home-owners will be notified separately as work comes close to their properties.

Detours: Bypassing the construction site using the below mentioned roads is recommended, wait times for local and through traffic could be up to 20 minutes.

  • Beaverton valley Road
  • 2 School House Road
  • Douglas Road
  • Bailer Hill Road

We will continue to keep residents informed as the project impact continues. If you have any questions or require more information project field contacts are listed below:

Josh Frizzell – Project Superintendent, Interwest Construction Inc. Cell: (360) 333-3184 josh (@) interwest (.) biz

Dan Reuss – Construction Manager, Brown and Caldwell. Cell: (602) 721-5751 dreuss (@) brwncald (.) com

You can support the San Juan Update by doing business with our loyal advertisers, and by making a one-time contribution or a recurring donation.


Categories: Around Here

No comments yet. Be the first!

Leave a Reply

Your email address will not be published. Required fields are marked *

By submitting a comment you grant the San Juan Update a perpetual license to reproduce your words and name/web site in attribution. Inappropriate, irrelevant and contentious comments may not be published at an admin's discretion. Your email is used for verification purposes only, it will never be shared.

Receive new post updates: Entries (RSS)
Receive followup comments updates: RSS 2.0